9. Manufacturing Strategy
Fulvio Federico
96
Evolution to a product-based business to most efficiently serve growing global demand
Project business | Technology provider and product business | |
Full customization per project | thyssenkrupp nucera green hydrogen business | |
prepared for being highly standardized with | ||
20 MW module |
>20 MW water
electrolysis plant
Standardized
20 MW module
Key benefits
Standardization and serial production
1 to achieve GW scale ensuring quality, schedule and cost optimization
2 | Establish thyssenkrupp nucera as a |
key technology provider |
3 | Reduction of complexity and risks by |
standardization |
thyssenkrupp nucera business in transition from a classical project business to a future AWE product-based business
97
thyssenkrupp nucera provides meaningful value-add across each step of the manufacturing process
thyssenkrupp nucera | + |
A cell design |
Fabrication of skid- | = | 20 MW module |
B mounted process units | C assembly |
CathodeAnode
thyssenkrupp nucera supply chain of cell components:
- Half shells manufacturing according to thyssenkrupp nucera's IP design (De Nora)
-
Electro-catalyticcoating and production techniques
(De Nora) - Other cell components
thyssenkrupp nucera supply chain of process & plant equipment:
- Tanks, pumps, filters
- Piping, valves & heat exchangers
- Electrical, instrumentation and control
- Power electronics
Single element
thyssenkrupp nucera assembly:
- Assembly of cells at customers' site or at thyssenkrupp nucera workshop
- Assembly of process units at customers' site
(e.g. separator / diaphragm, gasket frames and sealing, bolted flange, insert and distribution pipes, fittings and hoses for connection to the headers)
thyssenkrupp nucera's AWE business follows a holistic serial fabrication concept to capture demand
98
- thyssenkrupp nucera and De Nora already set up today to deliver 1 GW p.a.
Half shells production
Rodenbach
Further capacity expansion into other | |
thyssenkrupp | regions are planned |
nucera supply chain | Customer site or |
of cell components | |
module yard | |
thyssenkrupp nucera supply chain for cell components fully established & synchronized with De Nora to deliver 1 GW of electrolyzer p.a.
99
Video | How to achieve the energy transformation?
100
Um den Rest dieser Noodl zu lesen, rufen Sie bitte die Originalversion auf, und zwar hier.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
ThyssenKrupp AG published this content on 13 January 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 13 January 2022 13:40:12 UTC.