Yangarra Resources Ltd. reported production results for month of December 2013. the company's December 2013 production averaged approximately 3,000 boe/d.

The company also provided operational update for the year 2014. Yangarra's contracted drilling rig commenced operations after the Christmas break on a two well pad (1.75 net Cardium wells) in Willesden Green on December 28, with the first well now drilled and the second well on the pad expected to be rig released January 23, 2014. Completion operations will commence on January 24, with a frac date booked for January 28, 2014. The company expects to drill 4 gross (4.0 net) additional wells prior to breakup and with an additional two well pad ready (2.0 net wells) in the event that breakup is later than expected. Yangarra has identified 30 Cardium and Glauconite locations that could be developed with long reach (1.5 mile & 2 mile) horizontal wells. Yangarra plans to drill its first long-reach horizontal well after spring breakup in 2014. The company's current production is approximately 3,300 boe/d.