W Resources Plc announced that the La Parrilla tailings project located in southwest Spain, has been granted approval by the Mining Department of the regional authority of the Junta de Extremadura. The La Parrilla tailings project is expected to be in production in second half 2013 with annual plant feed in the region of 330,000 tonnes and annual production anticipated to be 28,000 MTU Tungsten (W) and 26 tonnes Tin (Sn), which at the current tungsten and tin prices should deliver approximately €7 million per annum in revenue. Construction of the processing plant located to the south east of the La Parrilla site will commence in first quarter 2013 and capital cost is estimated to be €1.3 million, for which the board are currently evaluating financing options.