Vestas Wind Systems A/S has received a 34MW order from Kangal Elektrik Uretim A.S to construct the Phase II of Kangal RES wind power plant in the Sivas province, Turkey. The contract also includes an eight-year full scope Active Output Management (AOM 4000) service agreement. Turbine delivery is scheduled for the third quarter of 2015, with commissioning expected in the fourth quarter of 2015.

This is the second phase of Kangal Elektrik's ambitious first wind project. The first phase, Kangal RES, is already operating with 22 V100-2.0 MW wind turbines providing green energy to approximately 227,000 people in Turkey. Once fully operational, the second phase of this project will provide additional electricity capacity to power approximately 200,000 people in the country.