Sandfire Resources NL is pleased to provide a pictorial update on the ongoing progress of construction and infrastructure development at DeGrussa.

ï'· Construction of DeGrussa mine and infrastructure progressing well, with the overall project now +60% complete.

ï'· Underground mine development is progressing on schedule with the "Evans Decline" currently advanced 1,000 metres from the portal, with approximately 300 metres of decline development remaining before the first ore is accessed.

ï'· Open pit mining is progressing on schedule with a total 5 million bank cubic metres (bcm) of material mined to date from the Stage 1 open pit, which is over 60 per cent complete. The open pit is currently at a depth of 45 metres below surface with oxide copper mineralisation now exposed and the floor is approximately 10 metres above Direct Shipping Ore (DSO).

ï'· The Company remains on track to mine the first of the high-grade DSO from the open pit in March 2012.

ï'· Installation of major infrastructure is progressing well with construction of the workshop and warehouse facilities well advanced and the power station expected to be commissioned in February.

ï'· Construction of the 1.5Mtpa DeGrussa concentrator significantly progressed with construction of major concrete foundations for the SAG Mill, Ball Mill and crushed ore bin completed and first steel fabrication underway.

ï'· The DeGrussa Aerodrome is well advanced, with earthworks completed and the aerodrome on schedule to be operational in February. 9

The text for this noodl has been truncated. To continue reading this document, please get the original version at: http://docs.noodls.com/viewDoc.asp?filename=71726/EXT/E305FB79C401C6C4DBB0179EE80BEE6619E8FC00_9BA3EA41EA56C10F851D7F99AB00EC9A6DBDEEF5.PDF

distribué par

Ce noodl a été diffusé par Sandfire Resources NL et initialement mise en ligne sur le site http://www.sandfire.com.au. La version originale est disponible ici.

Ce noodl a été distribué par noodls dans son format d'origine et sans modification sur 2012-01-24 07:45:27 AM et restera accessible depuis ce lien permanent.

Cette annonce est protégée par les règles du droit d'auteur et toute autre loi applicable, et son propriétaire est seul responsable de sa véracité et de son originalité.

Documents associés
DeGrussa Project Pictorial Update