Rail Vikas Nigam Limited won the contract worth of INR 6,738 million from Gujarat Metro Rail Corporation Limited for Supply, Erection, Testing and Commissioning of Power Supply Receiving & Distribution System, 750V DC Third Rail Traction Electrification and SCADA System for Surat Metro Rail Project Phase-I. Time period by which the order(s)/contract(s) is to be executed: 19 months. Also won contract worth INR 3,843 million from Gujarat Metro Rail Corporation Limited for Supply, Erection, Testing and Commissioning of Power Supply Receiving & Distribution System, 750V DC Third Rail Traction Electrification and SCADA System for Ahmedabad Metro Rail Project Phase-II. Time period by which the order(s)/contract(s) is to be executed: 19 months.