Platinum Australia Limited (ASX:PLA) is pleased to provide an
update on the progress made since initiating the transition
from contract mining to Owner Operator in January.
PhokaThaba Platinum ("PTP"), the PLA subsidiary which owns
the Smokey Hills Mine, took over day to day management of the
mining operation and associated activities effective 16
January. As part of the move to Owner Operator, PTP was
required to offer employment to all of the employees of the
mining contractor who wished to continue working at the mine.
The process of transferring the ex-employees of the
contractor was largely completed between February and
mid-March.
Since the changeover to Owner Operator on 16 January
significant improvements in almost all areas of production
have been recorded. The table below summarises some of the
key average daily production statistics achieved from the
beginning of January through until the 23rd
March.
January 1 - 152 | January 16 - 31 | February | March 1 - 13 | March 14 - 233 | |
Average Stope Metres Broken/day1 Average Tonnes Broken/day1 Average Tonnes Trammed/day1 | 185 1,226 1,094 | 230 1,677 1,352 | 216 1,237 1,487 | 204 1,290 1,235 | 290 2,040 1,890 |
1 - The underground mining operation operates on an 11 day fortnight, with an average of 23 production days per month allowing for Public Holidays.
2 - Underground mining operations carried out by Contractor during first two weeks of January.
3 - Based on daily figures, subject to final survey.
The period of 1 - 15 January was under the management of the
contractor, while the 16 - 31 January was the first period
under the management of PTP, and as can be seen, there was a
significant improvement in all key areas of production.
During February and the first half of March the transfer of
employees from the mining contractor to PTP was occurring and
some disruption in operations occurred. Despite this,
production was still above that achieved by the contractor
during the first half of January with no increase in mining
dilution.
As a result of the decision by PTP to take over as Owner
Operator, a total of 852 employees elected to transfer over
to PTP, including almost 100 senior, supervisory and
management personnel. Over the last month there have been
some 30 terminations, including 8 at the senior, supervisory
and management level. A total of 9 new employees have been
recruited, all at the supervisory management level. The
current levels of production are therefore being achieved
with less labour
Platinum Australia Limited
Level 3, 18 Richardson Street West Perth Western Australia 6005 Australia
T: + 61 8 9324 1494 F: + 61 8 9226 4259 E: pla@platinumaus.com W: www.platinumaus.com.au
One of the main areas which has proved challenging has been
in tramming ore from underground to the plant due to poor
equipment availability resulting from inadequate maintenance
by the contractor during previous months. . A program of work
to correct this was initiated in January and a significant
improvement is already evident with average tonnes trammed
per day over the last two weeks up over 60% from that
achieved by the contractor in the first half of January.
Underground production over the last week has exceeded
production ramp-up budget level (80% of full production) and
the Company expects production performance to continue to
improve over the next quarter as the systems and procedures
covering key areas such as training, management, personnel,
planning and maintenance which have been introduced as part
of the transition to Owner Operator become fully
established.
PLATINUM AUSTRALIA LIMITED
JOHN D LEWINS
Adam Reynolds/Guy McDougall
Newgate Threadneedle
+44 (0) 20 7653 9842
Media enquiries Australia:John Lewins
+61 8 9324 1491
M: +61 419 910 061
Platinum Australia Limited
Level 3, 18 Richardson Street West Perth Western Australia 6005 Australia
T: + 61 8 9324 1494 F: + 61 8 9226 4259 E: pla@platinumaus.com W: www.platinumaus.com.au
distributed by | This press release was issued by Platinum Australia Limited and was initially posted at http://www.gtp.com.au/platinumaus/inews_files/ASX1224JDL_260312.pdf . It was distributed, unedited and unaltered, by noodls on 2012-03-26 03:48:22 AM. The issuer is solely responsible for the accuracy of the information contained therein. |