Fax Coversheet



PALADIN ENERGY LTD

ACN 061 681 098


18 January 2016


ASX Market Announcements Australian Securities Exchange 20 Bridge Street

SYDNEY NSW 2000

By Electronic Lodgement


Dear Sir/Madam


QUARTERLY ACTIVITIES REPORT FOR PERIOD ENDING - 31 DECEMBER 2015



HIGHLIGHTS


  • Sales of 1,698,517lb U3O8at an average selling price of US$37.90/lb (vs. average spot price of US$36.03/lb)


  • Langer Heinrich Mine
    • Accounting production 1,258,833lb U3O8and drummed production 1,263,882lb U3O8,up 16% and 5% respectively vs. last quarter.

    • Average plant feed grade of 714ppm U3O8.

    • Overall recovery of 88.5%.

    • Record low quarterly C1 cash cost of production of US$25.38/lb (vs. guidance of US$25.00/lb to US$27.00/lb).

    • Record low monthly C1 cash cost achieved during the month of December of US$23.73/lb.


  • Kayelekera Mine
    • Newly commissioned Nano-filtration unit provided treated water meeting all discharge licence criteria and World Health Organisation, Malawi, and Australia drinking water guidelines.

    • Application for renewal of licence to discharge treated water approved by the Technical Committee of the Water Resources Authority and is awaiting Ministerial review.


  • Cash and cash equivalents at 31 December 2015 of US$136.8M (an increase of US$28.4M from 30 September 2015 and better vs. guidance pro-forma US$122.5M to US$132.5M after adjusting for the additional repurchase of Convertible Bonds due in April 2017 and sales proceeds from the last physical delivery of the quarter)


  • Repurchased an additional US$17M of the Convertible Bonds due April 2017 for approximately US$15.5M


  • An additional three Japanese reactors (Takahama 3 & 4 and Ikata 3) were cleared for re-start in the December quarter and are expected to commence operations in early 2016


  • Company continues to be on track to be cash flow neutral on an 'all in' basis at current spot uranium price and foreign exchange rates excluding one-off restructuring costs and capital management or strategic initiatives for FY16 full-year



Level 4, 502 Hay Street, Subiaco, Western Australia 6008 Postal: PO Box 201, Subiaco, Western Australia 6904

Tel: +61 (8) 9381 4366 Fax: +61 (8) 9381 4978 Email:paladin@paladinenergy.com.au Website: www.paladinenergy.com.au

SAFETY


The Company achieved 544 Lost Time Injury (LTI) free days at the Kayelekera Mine (KM) and 13 LTI free days at the Langer Heinrich Mine (LHM) at the end of this quarter.


The Company's 12 month moving average Lost Time Injury Frequency Rate (LTIFR) was 2.10 as compared to 1.39 at the end of the last quarter and 4.14 for the quarter to 31 December 2014.


The increase in the LTIFR in this quarter was a result of two lost time injuries at LHM. The lost time injuries were as follows:


  • A process operator sustained caustic burns when his Tyvek protective suit became torn and or saturated while moving in and out of a caustic tank.

  • A cleaning contractor slipped and fractured a bone in her foot whilst changing clothes in the change house.


QUARTERLY URANIUM SALES


Total sales for the quarter was 1,698,517lb U3O8at an average selling price of US$37.90/lb, generating gross sales revenue of US$64.4M, which was a 75% increase over the previous quarter's revenue.


The TradeTech weekly spot price average for the December quarter was US$36.03/lb.


LANGER HEINRICH MINE, NAMIBIA (75%)


Production and cash cost of production


2014

Dec Qtr

2015

Mar Qtr

2015

Jun Qtr

2015

Sep Qtr

2015

Dec Qtr

Accounting production (lb U3O8)

1,376,578

1,234,325

1,336,826

1,082,983

1,258,833

C1 cash cost of production (US$/lb)

28.58

29.42

26.03

27.82

25.38


Quarterly accounting production of 1,258,833lb U3O8was up on the preceding quarter by 16%. The amount of drummed material produced (i.e., drummed production) for the quarter was up 5% from last quarter to 1,263,882lb U3O8. We anticipate a continued trend of drummed production exceeding accounting production (i.e., release of material from in-plant inventory) for the remainder of FY16.


LHM unit C1 cash cost of production for the quarter decreased by 9% from US$27.82/lb in the September quarter to a record low US$25.38/lb. Unit C1 cash cost of production was 11% lower than in the quarter to 31 December 2014.


LHM achieved a record low monthly unit C1 cash cost of production in the December month of US$23.73/lb.


Guidance previously provided was for LHM unit C1 cash cost of production for the December quarter to be within the full-year guidance range of US$25.00/lb to US$27.00/lb.


Mining

2014

Dec Qtr

2015

Mar Qtr

2015

Jun Qtr

2015

Sep Qtr

2015

Dec Qtr

Ore mined (t)

703,901

598,341

700,831

833,057

680,892

Grade (ppm U3O8)

928

868

792

705

757

Additional low grade ore mined (t)

183,341

353,664

354,559

811,805

535,358

Grade (ppm U3O8)

325

316

325

317

319

Waste (t)

4,119,374

4,021,724

4,143,019

4,679,474

5,334,716

Total Ore and Waste (t)

5,006,616

4,973,729

5,198,410

6,324,336

6,550,966

Waste/ore ratio

6.1

7.3

6.4

6.6

8.6


Mining production for the quarter was up 4% on the prior quarter. Mining activities were completed in Pits H4 and G3B while the current focus is in Pits H5A, H3, H3-South and G3A. Ore mining occurred in Pits H3, H4, H5A and G3B. Pit H3-South top/sub-soil stripping was completed and waste stripping will commence in the next quarter.

Ore (high and medium grade) mining for the quarter was below target both in tonnage and grade due to more waste stripping in Pit H5A, top/sub-soil stripping in Pit H3 extension as well as the actual mining sequence being varied from the budget sequence. For the next quarter, more ore will be mined.

Run-of-Mine (RoM) ore stockpiles decreased at the end of the quarter. Lower stockpile levels will remain due to the increasing ore-to-waste stripping ratio in the western ore body. The RoM medium grade is being supplemented by medium grade ore from long-term stockpiles in line with the life of mine plan.


Processing

2014

Dec Qtr

2015

Mar Qtr

2015

Jun Qtr

2015

Sep Qtr

2015

Dec Qtr

Ore milled (t)

916,576

860,337

886,520

847,016

903,187

Grade (ppm U3O8)

773

736

778

706

714

Overall recovery (%)

88.2

88.4

87.8

82.2

88.5

Accounting production (lb U3O8)

1,376,578

1,234,325

1,336,826

1,082,983

1,258,833


Accounting production for the December quarter was up 16% on the prior quarter mainly due to a 7% increase in throughput and a 6% increase in overall recovery. However soluble recovery was below budget caused by lower than budget tailings density as a result of poor settling ore, worn cyclones and CCD thickener #7 centre well bogging. In addition, ion exchange performance was also lower than budget caused by poor performance from the BRP plant from late November, which resulted in higher barren liquor being returned as CCD circuit wash water as more concentrated eluate bypassed the circuit due to membrane fouling. The cyclone issue has been resolved while the BRP membrane issue is in progress. Modifications to CCD thickener #7 centre well are being investigated.


Innovation / optimisation


An external review of LHM's processing operations was undertaken by a third-party consultant during the quarter, resulting in a number of action items. Such items include a heavy focus on initiatives to increase plant operating uptime, which combined with other innovations already in the implementation or design phase, will be rolled out in the remainder of FY16 and FY17.


KAYELEKERA MINE, MALAWI (85%)


Operations


The Kayelekera Mine (KM) remains on Care and Maintenance.


Quarterly activities at site focussed on water treatment testing during October and November using filtration only. The water quality was good throughout the testing period with successful rejection of uranium and sulphate removal. Controlled treated water release will recommence in 2016 when the Malawi Government has renewed KM's licence for the discharge of treated water.


Exploration


Government of Malawi Parliamentary approval of, and the introduction of the new Mining Act in Malawi is still ongoing, as a consequence the Malawi Mines Department has delayed the issue of all licences until a new cadastral system has been introduced and all overlapping tenure issues have been resolved. It is expected that this process will be completed in the first half of 2016.


The Company continues to monitor the situation and liaise with the Malawi Mines Department to ensure that the introduction of the new legislation goes as smoothly as possible.


Exploration in the December quarter continued the surface geophysical surveys, stream sediment sampling and geological mapping previously started in areas around the mine on ML152 and EPL225. Analysis of the data obtained to date on these studies is ongoing.


MANYINGEE-CARLEY BORE PROJECT, WESTERN AUSTRALIA (100%)


Manyingee


A regional and local conceptual groundwater model for the greater Manyingee area was completed by external consultants during the quarter. The report is expected to be finalised in the March quarter following review by Company staff. The groundwater study, along with detailed geological modelling of areas suitable for in-situ recovery field leach trials (FLT), is expected to be used to complete an FLT application document in the first half of 2016.

Carley Bore


State government approvals for exploration drilling were finalised to allow for proposed drilling in FY17. Subsequent to the completion of the drill hole database audit a 3D geological model of the host stratigraphy and the redox front related to mineralisation was created. The 3D geological model has identified potential extensions to known mineralisation which are expected to be tested during future drilling campaigns.


AURORA-MICHELIN URANIUM PROJECT, CANADA (100%)


Results have been received for the orientation soil sampling survey completed over the Michelin and Rainbow deposits and surrounding areas during the northern summer field season. The aim of the survey was to confirm that Michelin style deposits can be identified through the existing cover sequence and additionally identify prospective areas adjacent to the existing deposits. Analysis of the results is currently underway and it is expected that initial planning for follow-up surveys and ground truthing will be completed in the first half of 2016 in order to make efficient use of any limited summer field season.


Analysis of the geophysical studies completed in the previous quarter is currently underway and the results will be used to enhance the regional prospectivity mapping that has already been commenced. It is expected that, when combined with the results from the orientation soil survey, prospective areas under cover will be more easily identified. It is hoped that this work can be completed sufficiently ahead of any exploration re-start in order to quickly identify readily accessible drill targets.


MOUNT ISA URANIUM PROJECTS, QUEENSLAND (82% to 100%)


Radiometric ore sorting tests for samples from the Odin, Bikini, Andersons, Watta, Duke Batman and Honey Pot deposits are currently underway at ANSTO. It is expected that the majority of the sorting samples will progress through to subsequent leach testwork during the remainder of 2016. Once the results from the leaching testwork have been received the results will be incorporated into an updated optimisation study for the project.


CORPORATE


Financial


In November and December 2015, Paladin repurchased US$17.0M of the Convertible Bonds due April 2017. The cash expenditure for the repurchase was approximately US$15.5M as the bonds were bought back at an average price of 90.6 per cent. The repurchase of US$17.0M in the December quarter together with the repurchase of US$20.0M in the September quarter (i.e., combined total of US$37.0M), has reduced the principal amount outstanding of the Convertible Bonds due 30 April 2017 from US$274.0M to US$237.0M. Combined cash savings net of the purchase outlay resulting from Paladin's repurchase activities are approximately US$7.0 million in the form of avoided principal and coupon payments over the period to maturity of the 2017 Convertible Bonds.


At 31 December 2015, the Group's cash and cash equivalents were US$136.8M, an increase of US$28.4M from US$108.4M at 30 September 2015. Guidance previously provided was for the 31 December 2015 cash balance to be in the range of US$110M to US$120M, with such guidance provided prior to the implementation of the convertible bond repurchase in the December quarter and excluding the sales proceeds from the last physical delivery of the quarter of approximately US$28M in value, which resulted in adjusted guidance pro-forma for those items of US$122.5M to US$132.5M.


URANIUM MARKET


The TradeTech weekly spot price average for the December quarter was US$36.03/lb, representing a 1% decrease compared to US$36.48/lb for the prior quarter and a 4% decrease compared to US$37.66/lb for the quarter to 31 December 2014.


In late December, the Fukui District Court lifted an injunction that had prevented the re-start of Units 3 and 4 at Kansai's Takahama nuclear power plant in Japan. The court decision cleared the way for resumption of operations at the two units and fuel loading was completed for Unit 3 on 28 December. Takahama 3 is expected to re-start before the end of January 2016, with Unit 4 following in late February. Shikoku Electric's Ikata Unit 3 is also expected to resume operations in early 2016. With the Japanese reactor re-start programme finally gathering some momentum, at least eight units are expected to be operating by the end of 2016.

Paladin Energy Ltd. issued this content on 2016-01-18 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 2016-01-18 08:55:03 UTC

Original Document: