In the first half of 2022, the Company completed the procurement of major equipment, the building of the plant structures, the construction of a loading ramp capable of supporting heavy dump trucks used for feedstock delivery, fabricated the feedstock chute, moved fixed equipment to site, and installed upgraded water recirculation and treatment systems.
Later in the year, Newlox Gold’s construction team moved on to fabricate the fine ore bin on-site at the
With the equipment positioned at the site, the final installation of material handling systems was underway over the winter. Principally, custom-made conveyor systems were installed to connect the dry portions of the processing plant, while slurry pumping infrastructure was fabricated and installed to move liquified feedstock through the plant.
Newlox’s operations team expects the commissioning and testing of the new processing facility to take approximately 1.5 to 2 months, followed by a gradual ramp-up of operations and precious metals recovery over the year. Simultaneously, the Company’s local mining partners are undertaking upgrade work at many of the nearby tunnels within the historic
The company looks forward to expanding cooperative efforts throughout the mining camp. Results to date have been very pleasing, and excellent rapport has been established with both the community and the cooperative miners. The entire mining community is rejuvenating with the planned modernization of the mining camp.
A Message from
“We are delighted to announce the completion of the construction phase at Newlox Gold’s second environmentally and socially positive precious metals recovery facility in
Although artisanal mining has a long and rich history in this area, traditional metal extraction methods can have harmful environmental consequences. By providing access for local mining groups to modern mineral processing technology,
Forward-Looking Information
The information in this news release includes certain information and statements about management’s view of future events, expectations, plans and prospects that constitute forward-looking information. Forward-looking information includes, but is not limited to, the completion of the work programs currently underway and the results of these programs. These statements are based upon assumptions that are subject to significant risks and uncertainties. Because of these risks and uncertainties and as a result of a variety of factors, the actual results, achievements, or performance may vary materially from those anticipated and indicated by these forward-looking statements. The material risk factors that could cause actual results to differ include the risk that work undertaken by the Company may have unintended effects, the risk of delays in completing work, and the risk that the Company may not be able to raise sufficient funds and Force Majeure. Although the Company believes that the expectations reflected in the forward-looking information are reasonable, it can give no assurances that the expectations of any forward-looking information will prove to be correct. Except as required by law, the Company disclaims any intention and assumes no obligation to update or revise any forward-looking information to reflect actual results, whether as a result of new information, future events, changes in assumptions, changes in factors affecting such forward-looking statements or otherwise. Neither Canadian Securities Exchange nor its Regulation Services Provider (as that term is defined in the policies of the Canadian Securities Exchange) accept responsibility for the adequacy or accuracy of this release).
Technical Disclaimer
The Company advises it is not basing any decision to produce on a feasibility study of reserves demonstrating the economic and technical viability of the project and also advises there is increased uncertainty and specific economic and technical risks of failure associated with any production decision. Grab sample results included in any press release are not necessarily indicative of the mineralization in general for the deposit.
On Behalf of the Board,
Contact
Website: www.newloxgold.com
Email: info@newloxgold.com
Phone: + 1 604 256 0493
Join our Mailing List
Copyright (c) 2023 TheNewswire - All rights reserved.
Copyright (c) 2023 TheNewswire - All rights reserved., source