Mostostal Zabrze S A : Completion of construction works for the hoist tower of the "Janina VI" shaft Janina Coal Mine
October 18, 2019 at 02:20 am EDT
Share
On the investment related to the construction of the final surface and underground infrastructure together with the mining hoist shaft of the 'Janina VI' shaft (TAURON Wydobycie S.A. Zakład Górniczy Janina), works related to the reinforced concrete structure of the main structure - the hoist tower are coming to the end.
In addition, facade panels made of sandwich panels are being installed, and the first installation works inside the buildings have started. The main structural works of the shaft collar have been completed and assembly works of the crew platform building are coming to an end. External networks, roads, squares and narrow-gauge railways are also being built.
More info: https://gpbp.mz.pl/en/content/end-construction-works-hoisting-tower-janina-vi-shaft
Mostostal Zabrze SA published this content on 18 October 2019 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 18 October 2019 06:18:03 UTC
Mostostal Zabrze SA is a Poland-based holding construction company. The Company provides its project in four sectors: Industrial Construction, Power, Environmental Protection, and Transport Infrastructure. It offers contracting of facilities, industrial plants, process lines and revamp, erection of complete facilities and buildings, construction of sport facilities, transport infrastructure, and waste water treatment plants. It also provides structural steelwork and machinery constructions, radio and television masts and towers, ski lifts, cableways, aluminum elements such as curtain walls, windows and doors, commercial halls and pavilions, as well as such services as design, galvanizing of steel structure, transport and lifting equipment and training.