Ledong Xiangshui Photovoltaic Power Station (20MW), which was partially contracted by the 3rd Company of Wuhan Surveying-Geotechnical Research Institute Co. of MCC Group (WSGRI), was smoothly completed and connected to the grid for power generation on December 28, 2013.
The station is invested by Hainan Water & Power Group. As one of the first batch of surface power stations with benchmark price, it is located in the Xiangshui Power Plant in Ledong County of Hainan Province, designed with an installed gross capacity of 20MW. Under this project, WSGRI was awarded with the contracts for spiral post works. The Project Division conquered the negative factors such as complicated terrain, large slope at hilly area and high hardness of granite. In total, over 20,000 spiral posts were completed, which enabled the grid connection target at the end of 2013 to be realized on time, and thus the perfect performance of WSGRI was placed with a high premium by the employer.