only | Q4 FY22 Investor |
use | Update Presentation |
ersonal |
Approved by the Board of Genex Power Limited
Diverse renewable energy | KIDSTON CLEAN ENERGY HUB |
project portfolio | 50MW Kidston Solar Project (Operating) |
only | 250MW/2000MWh Kidston Pumped Storage |
Hydro Project (Construction) | |
By 2025 our portfolio of | Up to 200MW Kidston Wind Project |
renewable energy and storage | (Development) |
Up to 270MW Kidston Stage 2 Solar Project | |
projects will provide clean | |
(Feasibility) | |
energy to over 350,000 homes | |
use | |
offsetting up to 2mtpa of CO2 | BOULDERCOMBE BATTERY PROJECT (BBP) |
emissions | 50MW/100MWh Large-Scale Battery Energy |
ersonal | Storage System "BESS" (Construction) |
JEMALONG SOLAR PROJECT (JSP) | |
50MW Jemalong Solar Project (Operating)
2
Q4 FY22 Activities Update
Kidston Solar | Jemalong Solar |
50MW | |
50MW | |
only |
K2-Hydro | Bouldercombe |
Battery Project | |
250MW/2000MWh | |
50MW/100MWh Large | |
Scale Battery Energy | |
Storage System |
• Revenue totalled $4.8M1 | • | Revenue generated on a merchant | |
• Generation of 26,334MWh of renewable | basis totalled $3.8M1 | ||
energy for the period | • | Revenue comprised of $3.0M1 from | |
• Average price of $182/MWh for the | electricity sales and $0.8M1 from LGC | ||
sales | |||
use | period2 | ||
• Generation of 17,044MWh of renewable | |||
energy for the period | |||
• | Average bundled price of $209/MWh for | ||
ersonal | |||
the period | |||
- The project remains on schedule and within budget for energisation in H2 FY25
- Key site activities and works undertaken during the period included:
- Completion of ~45% of the Main Access Tunnel;
- Surface blasting for the Wises Dam intake Canal;
- Geo-technicalworks for the Powerlink 186km transmission line to connect the project; and
- Commencement of construction of the Wises Dam, approximately 17% of the 7km embankment completed.
- Detailed design near finalised, onsite construction activities scheduled for Q1 FY23
- Tesla Megapacks due to arrive at the site in Q3 FY23
- Project on track for energisation by end of H2 FY23 and positioned to capitalise on the recent market conditions
Renewable Energy, On Tap | Q4 FY2022 Investor Update |
1. | Revenue figures are on an unaudited basis | 3 |
2. | Average price per MWh doesn't include the sale of LGCs |
Q4 FY22 operational and performance overview
ersonal use only
Q4 FY22 | Q4 FY22 | ||||
Total generation | Revenue of | ||||
43,378MWh | $8.6 million | ||||
Full year FY22 | Full year FY22 |
Total generation | Revenue of |
223,517MWh | $26.1 million |
Q4 FY22
Positive Cash flow from operations
$3.5 million
Full year FY22
Positive Cash flow from operations
$4.0 million
Cash position of
$62.9m
As at 30 June 2022
Full year FY22
Lost time injury = zero Environmental incident = zero
Renewable Energy, On Tap | Q4 FY2022 Investor Update
Revenue figures are on an unaudited basis | 4 |
Energy and LGC pricing - 2021 vs. | Average Black Electricity Regional | |||||||||||||||||||||
2022 | Reference Price (RRP) $/MWh | |||||||||||||||||||||
$600 | ||||||||||||||||||||||
$500 | ||||||||||||||||||||||
• 2022 has seen a rapid increase in black electricity prices in NSW | $400 | |||||||||||||||||||||
$300 | ||||||||||||||||||||||
and QLD caused by: | ||||||||||||||||||||||
$200 | ||||||||||||||||||||||
only | • Increases in international coal and gas prices; and | $100 | ||||||||||||||||||||
$- | ||||||||||||||||||||||
• | Baseload (coal) generators undergoing scheduled and non-scheduled | Oct-21 | Nov-21Dec-21Jan-22Feb-22Mar-22Apr-22May-22Jun-22Jul-22 | |||||||||||||||||||
maintenance. | Qld Average RRP | NSW Average RRP | ||||||||||||||||||||
Source: AEMO data | ||||||||||||||||||||||
• Large Scale Generation Certificate (LGC) prices have increased | LGC Price | |||||||||||||||||||||
from ~$41.00 in Sept 2021 to ~$50.75 in July 2022 | $52 | |||||||||||||||||||||
use | • LGCs are generated for every MWh produced, forming an additional | $50 | ||||||||||||||||||||
revenue source for renewable energy generators | $48 | |||||||||||||||||||||
• Both KS1 and JSP have been significant beneficiaries of this | $46 | |||||||||||||||||||||
$44 | ||||||||||||||||||||||
increase in pricing | ||||||||||||||||||||||
ersonal | $42 | |||||||||||||||||||||
$40 | ||||||||||||||||||||||
Oct-21 | Nov-21Dec-21Jan-22Feb-22Mar-22Apr-22May-22Jun-22Jul-22 | |||||||||||||||||||||
Source: Genex sourced figures | ||||||||||||||||||||||
Renewable Energy, On Tap | Q4 FY2022 Investor Update | 5 | |||||||||||||||||||||
This is an excerpt of the original content. To continue reading it, access the original document here.
Attachments
- Original Link
- Original Document
- Permalink
Disclaimer
Genex Power Ltd. published this content on 25 July 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 25 July 2022 22:48:01 UTC.