15 October 2010
ASX/Media Release - 28 March 2012
Credit Approved Commitment for $42M Financing Package received from Deutsche Bank Construction set to start by year-end, with first production scheduled in 2013 Key Points:• Deutsche Bank provides credit approved commitment for
A$42M financing package• Overall development financing package targeted for completion in Q3 2012, with development planned to follow soon thereafter
Australian gold company Cortona Resources Limited (ASX: CRC)
is pleased to advise that it is on track to begin development
of its flagship Dargues Reef Gold Project in NSW, having
signed a credit approved commitment letter with Deutsche Bank
AG ("Deutsche Bank"), Sydney Branch, in respect of an A$42
million financing package to underpin project
construction.
This important milestone follows extensive due diligence
conducted by Deutsche Bank since it was mandated to provide
the financing package in August last year, as well as the
receipt of key State and Federal environmental approvals for
the Dargues Reef Gold Project last month.
The financing package remains subject to a number of
conditions precedent customary for financing arrangements of
this nature, including final regulatory approval for the
transport of gold concentrate off-site to the mothballed
London Victoria treatment plant located at Parkes. Cortona
will operate this plant, which is now on care and
maintenance, but was previously owned and operated by BHP
Billiton.
The Dargues Reef Gold Project, which is located near
Braidwood approximately 60km south-east of Canberra in NSW,
is expected to be one of the few Australian gold projects
which this year will move from feasibility to development,
and into production next year.
Cortona R esources Limited Level 5, 72 Kings Park R oad W est Perth, W A 6005
Postal AddressPO Box 86, W est Perth W A 6872
Websitewww.cort onaresources.com.au
Emailadmin@cort onar esources.com. au
Phone(08) 9485 0577
Facsimile(08) 9485 0706
ABN: 98 117 848 790 ASX CODE: CRC Corporate Information(29 February 2012)
Shareholders ~2,300
Shares on Issue 221M Options (Unlisted) 17M
PROJECTS Majors Creek (NSW) Eugowra (NSW) Christmas Gift (NSW) Booths Reward (NSW)1
Cortona's Managing Director, Peter van der Borgh, said
receipt of the commitment from Deutsche Bank represented a
key milestone for the Company, effectively laying the
foundations for completing the overall financing package and
the commencement of mine development and construction.
"This key development should enable us to move ahead with
completion of an overall debt and equity financing package."
Mr van der Borgh commented.
The timetable to production for the Dargues Reef Gold Project
is now forecast to be:
• Receipt of Environmental Protection License - Q2 2012
• Grant of Mining Lease by NSW State Government - Q2 2012
• Council approval for transportation of gold concentrate
off-site to Parkes - Q2 2012
• Approval to utilise paste-fill in underground mine - Q2/Q3
2012
• Completion of overall project financing package - Q3
2012
• Commencement of construction - Q4 2012
The Dargues Reef Gold Project will be an underground mine
feeding a 330,000tpa on-site plant, with forecast production
ramping up to a peak rate of ~65,000oz per annum, and
averaging 50,000ozpa over the life of mine, at a forecast C1
unit cash operating cost of A$697/oz. This operating cost
includes a 10 per cent contingency.
The mine is forecast to generate free cash flow of ~A$125
million over its initial 6-year mine life, using a gold price
of A$1,550 per ounce. The robust economics of the project are
underpinned by the high grade of the deposit, which has an
undiluted grade of 7.25g/t Au.
Ore will undergo crushing and grinding at the Dargues Reef
site, with 50 per cent of the gold recovered via gravity
methods on site and the balance recovered from a pyrite-gold
concentrate (grading ~25g/t Au). The concentrate will be
transported approximately 400km to the London Victoria gold
treatment plant near Parkes which Cortona will operate to
recover gold bars.
"We are targeting financing to be completed during the third
Quarter of 2012, once we satisfy the conditions precedent
including receipt of the outstanding regulatory approvals,
which are largely procedural" Peter van der Borgh said.
The Financing Package includes a prepaid gold forward and
requires Cortona to commit to a gold hedging program
("Hedging Program"). The total quantum of gold ounces
committed under the Financing Package will be dependent upon
the prevailing spot price at financial close but is expected
to represent approximately 30% of the existing proven and
probable reserves at Dargues Reef. The Hedging Program will
secure the Company's repayment obligations whilst
providing Cortona with significant exposure to the spot price
in this very strong gold market.
Yours faithfully
Peter van der Borgh
Managing Director
Managing Director
+618 9485 0577 or Nicholas ReadRead Corporate
+618 9388 14742
distributed by
| This press release was issued by Cortona Resources Limited and was initially posted at http://www.cortonaresources.com.au/files/announcements/274 - Deutsche Bank $42M Credit Approved Comm itment 28.03.2012.pdf?PHPSESSID=f446d9966e596df012f0270c7531ccb4 . It was distributed, unedited and unaltered, by noodls on 2012-03-28 04:35:15 AM. The issuer is solely responsible for the accuracy of the information contained therein. |