31 January 2017

December 2016 Quarterly Report

Highlights:
  • Development study work continued at Mahalo
  • Mahalo pilot maintains strong production rate
  • Transfer of ATP 1015 to Comet Ridge being finalised - Galilee basin area now 9685 km2
  • Successful $2.4m capital raising completed during the Quarter

A shortage of new natural gas supplies coming into the east coast market continues to generate significant market stress with no new gas exploration or development occurring in Victoria, New South Wales or the Northern Territory. This puts a strong focus on available reserves and resources in Queensland to meet the expanding east coast LNG and domestic gas demand requirement.

Comet Ridge believes that central Queensland (Galilee and Southern Bowen Basins) will be key in short to medium term gas supply. Detailed in the table below, is Comet Ridge's current (net recoverable) reserve and resource position for its Queensland tenures. The Company continues its dialogue with a number of parties in relation to gas supply from the Southern Bowen and Galilee Basins and the provision of infrastructure around that gas supply.

Comet Ridge Limited - Queensland Net Recoverable Reserves and Resources

Location

Project

COI

Interest

Reserve (PJ) 1

Contingent Resource

Prospective Resource (PJ) 2

1P3

2P

3P

1C

2C

3C

Southern Bowen Basin, QLD

Mahalo Gas Project

40%

-

30

219

112

232

372

-

(ATP 1191)

Galilee Basin, QLD

Gunn Project Area 4

100%

-

-

-

-

67

1,870

597 4

(ATP 744P)

Galilee Basin, QLD

Albany Structure

100%

-

-

-

56

153

417

-

(ATP 744P)

Total

-

30

219

168

452

2,659

597

See Notes to Table at Page 5

Comet Ridge Limited T: +61 7 3221 3661 E: info@cometridge.com.au 283 Elizabeth St, Brisbane, Qld, 4000 Australia

ABN 47 106 092 577 F: +61 7 3221 3668 W: www.cometridge.com.au GPO Box 798, Brisbane, Qld, 4001 Australia

ASX CODE: COI

Comet Ridge Limited

ATP 1191 Mahalo - Southern Bowen Basin, Qld (Comet Ridge 40%), Santos (30%), APLNG (30%)

The Mahalo pilot scheme continues its strong gas production performance (Figure 1) with low to negligible water rates. After a short shut-in during the quarter for maintenance work, the Mahalo pilot came back on line strongly. The Mahalo pilot is 14km from a pipeline connection.

Figure 1 - Mahalo pilot scheme gas and water production to end of the December quarter

During the quarter, Comet Ridge finalised its development analysis work to examine the most efficient and cost effective way to move the northern pilot schemes in the block into production via available export pipeline capacity and field infrastructure (Refer Figure 2).

These studies focussed on utilising existing infrastructure, wherever possible, to minimise capital spend and optimise the time required to initially bring the northern part of the Mahalo block into production. The Company also examined a southerly gas export option for Mahalo, which would be required to take the field production above 25 TJ/d given the pipeline volume constraints in the field infrastructure to the west.

Figure 2 - Potential Mahalo northern field layout for 25 TJ/d initial production phase

The 2017 Work Program and Budget for the Mahalo Joint venture is yet to be approved, however given that the 2017 year is well underway, this approval is expected to be imminent. This will then allow detailed scheduling of field work for this year to be finalised.

ATP 743 and ATP 744 - Galilee Basin, Qld (Comet Ridge 100%) ATP 1015 - Galilee Basin, Qld (Comet Ridge increasing to 100%)

Comet Ridge continues to work with a number of parties in relation to supply of gas from the Galilee Basin (both sandstone gas and CSG) and the associated infrastructure. There are several connection points and supply options available and the Company continues to evaluate the commercial inputs that provide the greatest optionality and value to the Company. LNG supply, industrial and domestic demand, and power generation sectors each have requirements for gas and may not be mutually exclusive - the volume of gas resources in the Galilee Basin is such that multiple requirements may be able to be met concurrently. Evaluation work continues on each of the options.

In ATP 1015, Comet Ridge has provided the final transfer documentation to the Queensland Government's Department of Natural Resources and Mines (DNRM) to take its equity to 100%.

Figure 3 - Regional Location of Mahalo JV Area and Eastern Galilee Basin Blocks

Comet Ridge has a very large acreage position in the eastern part of the Galilee Basin which is prospective for both sandstone gas and CSG development, including 100% interests in ATP 743 and ATP 744 and is increasing its interest in ATP 1015 to 100% (Refer Figure 3). The Company holds an acreage position in excess of 9685 km2 at the 100% equity level.

Gunnedah Basin, NSW (Comet Ridge CSG equity: PEL 427: 59.09%, PEL 428: 68.42%, PEL 6: 29.55%) (Comet Ridge Conventional equity: PEL 427: 100%, PEL 428: 100%, PEL 6: 99.7%)

The Company continues to wait for formal approval of the renewals for PEL 6, PEL 427 and PEL 428. It is unclear when these approvals will be granted although we understand they are continuing to be progressed. In keeping with the delay on the approval applications by the NSW government, the current spend on the permits is very low.

Figure 3 - Comet Ridge's Gunnedah Basin position

Corporate Activities

During the quarter, the Company completed a successful $1.4m Placement and a 1 for 25 Entitlement Offer to shareholders raising a further $1.05m. Both the Placement and the Entitlement Offer were offered at 5c per share. Demand for the stock saw the Placement strongly supported and the Rights issue heavily oversubscribed.

Stephen Rodgers Company Secretary Comet Ridge Limited

For further information please contact:

Tor McCaul

Managing Director

Comet Ridge Limited

tor.mccaul@cometridge.com.au

+61 7 3221 3661

Comet Ridge Limited published this content on 31 January 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 31 January 2017 05:44:07 UTC.

Original documenthttp://www.cometridge.com.au/PDF/2017 01 31 - COI - Quarterly Activities Report.pdf

Public permalinkhttp://www.publicnow.com/view/DDDCC5F325936D669E28BEED55920AEAB9A60A79