Cequence Energy Ltd. announced that the company completed the expansion of its 100 mmcfd facility at Simonette (13-11) and chose to move the commissioning of the facility from December, 2014 to January, 2015 to avoid higher costs and potential service quality issues over the Christmas season. Commissioning of the plant involved a full one week shut down of the entire Simonette field beginning on January 6th with a systematic one week step-up restart which commenced on January 13th. As of January 20th, total corporate production based on field estimates has ramped to 12,000 boepd with approximately 2,500 boepd to be turned on or restarted by February.