Quarterly Activities Report - December 2018

17 January 2019

HIGHLIGHTS

  • Net debt free at 31 December 2018 - a reduction of US$24.8m during the quarter.

  • Mined tonnes increased a further 5% to 5.0Mt, helping to offset lower ore grade.

  • Continued strengthening of rutile and zircon prices with the ilmenite price remaining stable.

  • FY19 production guidance revised, primarily due to ore characteristics being encountered in the remnants of the Central Dune orebody:

    • ◦ Rutile ‐ 88,000 to 94,000 tonnes (previously 88,000 to 93,000 tonnes).

    • ◦ Ilmenite ‐ 385,000 to 415,000 tonnes (previously 420,000 to 450,000 tonnes).

    • ◦ Zircon ‐ 31,000 to 34,000 tonnes (previously 32,000 to 37,000 tonnes).

  • No lost time or medical treatment injuries.

  • 136km2 Vanga prospecting licence granted, extending south west from the company's existing Kwale Operations.

  • Toliara Project continues to progress towards Pre‐Feasibility Study completion in Q1 2019.

African mineral sands producer, Base Resources Limited (ASX & AIM: BSE) (Base Resources or the Company) is pleased to provide a quarterly operational, development and corporate update.

The main focus at the Kwale Mineral Sands Operations (Kwale Operations) in Kenya, was maximising mineral recoveries under a high tonnage, low grade regime, together with preparations for relocating mining operations to the South Dune orebody in June 2019. The Company also continued to advance its exploration programs in pursuit of mine life extensions.

The Company progressed its Toliara mineral sands project (Toliara Project) in the south‐west of Madagascar with development of the selected mining, processing and infrastructure options as well as distribution of the first product marketing samples to customers. The project remains on track to complete the Pre‐Feasibility Study in the March 2019 quarter, ahead of delivering a Definitive Feasibility Study in the December 2019 quarter.

KWALE OPERATIONS

PRODUCTION

Dec 2017

Mar 2018

June 2018

Sept 2018

Dec 2018

& SALES

Quarter

Quarter

Quarter

Quarter

Quarter

Production (tonnes)

Ilmenite

119,209

111,630

114,773

118,265

108,465

Rutile

22,798

21,634

24,451

25,125

24,505

Zircon

9,569

9,166

9,286

9,683

8,252

Zircon low grade1

Sales (tonnes)

Ilmenite

119,554

140,665

107,170

107,632

106,788

Rutile

25,377

25,526

25,635

23,580

24,008

Zircon

8,144

9,884

9,007

8,507

8,063

Zircon low grade1

3,287

1 Zircon low grade tonnes contained in concentrate, equivalent to approximately 70‐80% of the value of primary zircon.

Mining continued in the Central Dune, again achieving higher than planned mining rates. Mined ore grades were lower than previous quarters, as expected, with all mining now located on the western and southern fringes of the orebody ahead of expected completion of Central Dune mining in the June 2019 quarter.

MINING & WCP

Dec 2017

Mar 2018

June 2018

Sept 2018

Dec 2018

PERFORMANCE

Quarter

Quarter

Quarter

Quarter

Quarter

Ore mined (tonnes)

2,882,529

1,883,159

3,543,430

4,791,969

5,036,211

HM %

7.61

6.88

6.36

4.78

3.60

HMC produced (tonnes)

196,725

125,298

192,559

199,079

148,937

Wet concentrator plant (WCP) production of heavy mineral concentrate (HMC) moderated in the quarter to 149kt (last quarter: 199kt) as a result of the lower mined ore grades. Consequently, HMC stockpiles decreased to 46kt (last quarter: 86kt) by quarter end. WCP mineral recoveries were also lower during the quarter due to the low ore grades and an increased percentage of oversize in the plant feed. Further optimisation of the spirals circuit during the second half of December remedied this issue and restored recoveries to close to target levels.

With the Tailings Storage Facility (TSF) outer wall complete, all sand tails were deposited into the mined‐out area of the Central Dune, representing the first stage of rehabilitation in this section. Rehabilitation of the outer wall of the TSF continued. Good rains throughout the quarter kept the Mukurumudzi Dam full.

MSP PERFORMANCE

Dec 2017

Mar 2018

June 2018

Sept 2018

Dec 2018

Quarter

Quarter

Quarter

Quarter

Quarter

MSP Feed (tonnes of HMC)

190,798

180,128

192,376

194,311

191,633

MSP feed rate (tph)

91

92

90

91

90

MSP recovery %

Ilmenite

100

101

100

101

102

Rutile

100

99

101

99

99

Zircon

77

78

79

79

73

Mineral separation plant (MSP) availability was good at 97% (last quarter: 97%) with a total of 192kt of HMC processed (last quarter: 194kt). The previously announced five‐day maintenance shutdown of the MSP, scheduled for November 2018, has been postponed to the September 2019 quarter, due to contractor availability.

Rutile production and recoveries were consistent with recent quarters at 24.5kt (last quarter: 25.1kt) and 99% (last quarter: 99%) respectively.

Ilmenite recoveries were higher at 102% (last quarter: 101%), but overall production dropped to 108.5kt (last quarter: 118.3kt) due to lower contained ilmenite in the feed, a trend that we expect to continue for the remainder of the Central Dune orebody.

Zircon recoveries reduced to 73% (last quarter: 79%), impacted by lower contained zircon in the feed, resulting in decreased production of 8.3kt (last quarter: 9.7kt).

Bulk loading operations at the Company's Likoni Port facility continued to run smoothly, dispatching more than 126kt of ilmenite and rutile during the quarter (last quarter: 128kt). Containerised shipments of rutile and zircon through the Mombasa Port proceeded according to plan.

SUMMARY OF UNIT COSTS

Dec 2017

Mar 2018

June 2018

Sept 2018

Dec 2018

& REVENUE PER TONNE (US$)

Quarter

Quarter

Quarter

Quarter

Quarter

Unit operating costs per tonne produced

$92

$98

$102

$103

$115

Unit cost of goods sold per tonne sold

$120

$114

$143

$124

$146

Unit revenue per tonne of product sold

$344

$314

$376

$354

$377

Revenue: Cost of goods sold ratio

2.9

2.8

2.6

2.8

2.6

Total operating costs were marginally higher than the previous quarter due to higher tonnes mined, which, when combined with a decrease in overall production volumes, resulted in a higher unit operating cost of US$115 per tonne produced (rutile, ilmenite and zircon) (last quarter: US$103 per tonne). Unit operating costs are higher than the same period last year (December 2017 quarter: US$92 per tonne) due to higher operating costs associated with a 75% increase in mining and WCP volumes following implementation of the Kwale Phase 2 mine optimisation project. Cost of goods sold of US$146 per tonne sold (operating costs, adjusted for stockpile movements, and royalties) (Q3: US$124) was higher than last quarter due to the drawdown of HMC stocks, resulting in an increase in cost of goods sold of US$0.4m (Q3: decrease in cost of goods sold of US$1.8 million as finished goods stocks increased).

Revenue per tonne of product sold varies significantly each quarter, with the number of bulk rutile sales during that quarter being the primary factor. In a year, there are typically seven or eight bulk rutile sales of approximately 10‐12kt each, which means any given quarter will usually contain either one or two of these sales. As annual rutile sales account for approximately 40% of revenue but only 15% of volume, the number of bulk rutile sales in a quarter has a significant bearing on revenue, but not sales volume. This quarter had two bulk rutile sales taking total rutile sales to 24.0kt, higher than last quarter's 23.6kt total rutile sales. Higher zircon and rutile prices in the quarter and steady ilmenite prices contributed to the average revenue per tonne increasing to US$377 per tonne (last quarter: US$354 per tonne).

MINING TRANSITION TO THE SOUTH DUNE

The planned transition of mining to the South Dune orebody has been advanced to June 2019 (previously scheduled for July 2019) due to mining the Central Dune orebody faster than anticipated over the past two quarters and an anticipated continuation of the lower than expected ore densities, and therefore lower ore tonnes, encountered while mining the remnants of the Central Dune orebody. Rescheduling of the mining transition to the South Dune will result in a two‐week shutdown of the WCP in June 2019. As a result, commencing February 2019, MSP feed rates will be lowered by 20% for a three‐month period, a month longer than originally planned, to ensure sufficient HMC stocks are available during the transition to the South Dune to allow continuous feed to the MSP. Production of ilmenite, rutile and zircon will be correspondingly lower during this time.

Engineering work, procurement, clearing and earthworks for the transition continued in the quarter with equipment deliveries commencing in December 2018. The total cost of works for the mine move are forecast to be US$12.3m and will be incurred over financial year 2019 (FY19). The project primarily involves the supply and installation of 7,400m of slurry and water piping, an 8,500m 11kV power line, a pipe bridge across the Mukurumudzi Dam spillway, a 1.25MW slurry booster pump and a 1MW process water booster pump. Total expenditure on the mining transition to the South Dune to date has been US$5.1m (last quarter: US$0.3m).

FY19 PRODUCTION GUIDANCE REVISED

Previous FY19

Revised FY19

Guidance Range

Guidance Range

Rutile (tonnes)

88,000 to 93,000

88,000 to 94,000

Ilmenite (tonnes)

420,000 to 450,000

385,000 to 415,000

Zircon (tonnes)

32,000 to 37,000

31,000 to 34,000

The revised FY19 production guidance is driven by a combination of:

  • An anticipated continuation of the lower ore densities (than previously forecast) seen while mining the remaining fringes of the Central Dune orebody. This means fewer available ore tonnes, thereby bringing forward the exhaustion of the Central Dune and the bringing forward of the move to the South Dune to June 2019 from July 2019 and the associated two week shut.

  • Mineral assemblage variations resulting in lower ilmenite content relative to rutile and zircon than previously forecast in the fringe ore zones.

FY19 production guidance is based on the following updated assumptions:

  • Mining of 17.9Mt (previously 18.3Mt) at an average heavy mineral grade of 3.88% (previously 3.98%), with the remaining volume all from Ore Reserves2.

  • MSP feed rate at an average of 86tph (previously 89tph), consistent with recent performance.

  • Mineral separation plant product recoveries of 101% for ilmenite (previously 100%), 99% for rutile (unchanged) and 76% for zircon (previously 77%), consistent with recent performance.

MARKETING

Global pigment producers have reported a moderation in demand through the traditionally slower December quarter, with some pigment end users and traders understood to have reduced their inventories. The Chinese domestic pigment market softened due to ongoing economic uncertainties, as did some of China's export markets following the US/China trade tensions.

However, as pigment producers in most major producing regions have continued to target maximum output, demand for feedstock remains high. Ongoing supply constraints in the high‐grade feedstock sector (including rutile) have maintained upward pressure on rutile prices. This will continue into the March 2019 quarter with solid price increases being contracted for upcoming rutile shipments.

Demand for ilmenite from the Chinese pigment industry was firm through the quarter with pigment producers increasing their output as the impact of environmental inspections diminished. Prices for both domestic and foreign ilmenite in China remained reasonably stable throughout the quarter, which is expected to continue through to the March 2019 quarter. Major global pigment producers indicate they expect the current end user pigment de‐stocking cycle to be completed during the March 2019 quarter, with demand increasing again through the seasonally strong June 2019 quarter.

Zircon demand weakened through the quarter as a result of global trade tensions and softer economic conditions across most markets. However, ongoing supply constraints have supported stable zircon prices which are expected to remain at the current high levels through early 2019. The extent of a rebound in zircon demand during the seasonally strong June 2019 quarter will largely depend on the general economic performance in China and other major zircon markets.

2 The Ore Reserves estimates underpinning the above production targets were prepared by Competent Persons in accordance with the JORC Code (2012 edition). The above production targets are the result of detailed studies based on the actual performance of the Kwale mine and processing plant. These studies include the assessment of mining, metallurgical, ore processing, environmental and economic factors.

SAFETY

With no lost time or medical treatment injuries occurring during the quarter or in the past year, the Company's lost time injury frequency rate (LTIFR) and total recordable injury frequency rate (TRIFR) remain at zero. This represents an exceptional performance reflective of the ongoing focus and importance placed on safety by management. Base Resources' employees and contractors have now worked 14.9 million man‐hours LTI free, with the last LTI recorded in early 2014. Further, 5.3 million man‐hours have been worked without a medical treatment injury.

LTIFR & TRIFR frequency rates

3

Western Australia all mines

LTIFR 2016/17

etaRycneuqerF

2

1

Base Resources TRIFR

Base Resources LTIFR

0

81‐naJ

81‐beF

81‐raM

81‐rpA

81‐yaM

81‐nuJ

81‐luJ

81‐guA

81‐peS

81‐tcO

81‐voN

81‐ceD

COMMUNITY AND ENVIRONMENT

Agricultural livelihood programs at Kwale, run in conjunction with partners Business for Development, DEG, FMO, Australia's DFAT and Kenya Red Cross, continue to develop with encouraging support from both national and county Kenyan governments. These programs have expanded to involve over 3,000 smallholder farmers and community groups.

Harvesting of cotton, pea and sorghum crops have been completed for this growing season with good results and the farmers' cooperative, PAVI, is now marketing the produce. In addition, beekeeping has developed into a leading income generator for participating farmers with good yields and consistent pricing.

More than 350 secondary scholarships were awarded to students from Kwale County in the quarter.

Rehabilitation of the tailings storage facility outer sand wall is underway with approximately 28% revegetated so far. Local women's groups have proven to be vital partners in the rehabilitation program, supplying grass seed and manufacturing erosion control materials.

At the Toliara Project, agreements are being put in place with local communes to formalise Base Resources' community development initiatives, including construction of water boreholes, a school and health facility over the next three years. Several local improvement projects have been carried out in each of the five local communes including flood protection, irrigation channels and preparations for the upcoming planting season.

BUSINESS DEVELOPMENT

TOLIARA PROJECT DEVELOPMENT ‐ MADAGASCAR

As the Pre‐Feasibility Study has progressed, Base Resources' has revised its development plan for the Toliara Project to now complete the Definitive Feasibility Study by the December 2019 quarter, ahead of a decision to proceed to construction in the March 2020 quarter. The full Pre‐Feasibility Study remains on target for completion in the March 2019 quarter. This timetable is still expected to have the Toliara Project in production in the December 2021 quarter.

Attachments

  • Original document
  • Permalink

Disclaimer

Base Resources Limited published this content on 17 January 2019 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 17 January 2019 03:23:08 UTC