NORTHEAST AEGEAN ISLANDS ARE INCLUDED TO THE TYNDP 2021-2030

The company 'ADMIE (IPTO) HOLDING S.A.' (or 'Company'), informs that its Αffiliate, Independent Power Transmission Operator


IPTO S.A., announces the inclusion of the Northeast Aegean Islands to the preliminary Ten-Year Network Development Plan (TYNDP) for the period 2021-2030, markingthe last major island interconnection project drafted for the next ten years. In more specific, IPTO SA proceeds to the implementation of the interconnection projects of the Northeast Aegean Islands and the Dodecanese islands, with a total budget of Euro 935 million and Euro 1.477 billion respectively, in three phases:
  • Phase A includes the interconnections linking HVC Corinth to Kos, Kos to Rhodes, HVC N. Santas to Limnos and Limnos to Lesvos, completed by 2027.
  • Phase B comprises the interconnections linking HVC Aliveri to Skyros, Lesvos to Chios, Kos to Samos and Rhodes to Karpathos, completed by 2028.
  • Phase C includes the completion of Transmission grids between Lesvos-Skyros and Chios-Samos interconnections, completed by 2030.

The preliminary TYNDP 2021-2030, with a total budget of Euro 4.4 billion, among others, comprises the completion of electricity interconnections in Crete and the Cyclades, the upgrade of the Ionian Islands Transmission Grid, the completion of the upgrade of the 400kV System in the Peloponnese, the enhancement of the 400kV System in the region of East Macedonia and Thrace and the expansion of international interconnections.

International Interconnections: The new TYNDP outlines the construction of the second interconnection line linking the Greek and Bulgarian Transmission Systems. The new 400 kV interconnection is a major pan-European project and is expected to be integrated into the European System at the beginning of 2023. In addition, the development of new interconnections and the upgrade of the existing ones with the neighboring Systems of Northern Macedonia and Turkey are also under examination. To this end, relevant feasibility studies will be carried out in the near future, to support the selection of projects that have to be included in the Ten-Year Development Plan of ENTSO-E and the respective National Development Programs.

RES Integration: Following the successful implementation of the new TYNDP, the upgraded Electricity Transmission System, combined with the transition of power production mix and the integration of new storage systems, promises to meet the needs of the new targets set by the National Energy and Climate Plan of 2030.

Mr. Μanos Manousakis, Chairman and CEO of IPTO SA stated: 'The Ten-Year Network Development Plan 2021-2030 includes for the first time the Northeast Aegean Islands, reinforcing the electricity interconnections across Greek Islands. The new TYNDP has significant environmental benefits and sets the conditions for higher integration of RES in power generation, according to the targets set by the national energy strategic plan. At the same time, the Operator monitors closely the energy developments in the SEE region and, in co-operation with ETSO-E, conducts new plans for further electricity interconnections with the focus on increasing its contribution to the integration of the single European electricity market. As far as the implementation of the investment plan is concerned, IPTO SA proceeds its projects without delays through optimal usage of its resources, in order to further accelerate electricity interconnections. '

Athens, January 3rd, 2020