The Company is working to advance Stage 2 of its planned direct shipping ore mining operations, which involves the development of its
RPA has to date substantially completed an updated mineral resource estimate and undertaken a detailed optimization of the open pit mining strategy and proposed production schedule. This expanded scope of work, which has taken additional time to complete, is focused on maximizing the component of the mineral resource that can benefit from the dry crushing and screening processing strategy and potentially increasing the production life of the project beyond 10 years.
The strategy aims to maximize the quantity of higher-grade mineralization and minimize the waste mined in the plan, thus lowering the strip ratio, with the objective of reducing overall costs. The revised mine plan is now scheduling distinct phases of mining in multiple smaller pits within the already permitted project footprint and is likely to result in a smaller overall disturbance area.
'While the completion of the study has been delayed by some weeks, the potential benefits in pursuing this detailed mine planning strategy, with the objective of maximizing the grade and reducing operating costs, are considered meaningful and important to the overall economics of the
The updated mineral resource estimate is expected to be completed by mid-February, with the results of the PEA expected to be available around the end of February, and the Technical Report expected to be filed before the end of the Company's current financial year ending
ABOUT
LIM continues to monitor iron ore market conditions as they relate to the availability of development financing.
In the three-year period of 2011, 2012 and 2013 LIM produced a total of 3.6 million dry metric tonnes of iron ore, all of which was sold in 23 cape-size shipments into the
LIM's current focus is on planning activities related to the development of its
Contact:
Tel: (647) 728-4105
Forward Looking Statement
Some of the statements contained in this News Release may be forward-looking statements which involve known and unknown risks and uncertainties relating to, but not limited to, LIM's expectations, intentions, plans and beliefs. Forward-looking information can often be identified by forward-looking words such as 'anticipate', 'believe', 'expect', 'goal', 'plan', 'intend', 'estimate', 'may' and 'will' or similar words suggesting future outcomes, or other expectations, beliefs, plans, objectives, assumptions, intentions or statements about future events or performance. Forward- looking information may include reserve and resource estimates, estimates of future production, unit costs, costs of capital projects and timing of commencement of operations, and is based on current expectations that involve a number of business risks and uncertainties and assumptions regarding financing. Factors that could cause actual results to differ materially from any forward-looking statement include, but are not limited to, failure to establish estimated resources and reserves, the grade and recovery of ore which is mined varying from estimates, delays in obtaining or failures to obtain required financing, capital and operating costs varying significantly from estimates, delays in obtaining or failures to obtain required governmental, environmental or other project approvals, delays in the development of projects, changes in exchange rates, fluctuations in commodity prices, inflation and other factors. Forward-looking statements are subject to risks, uncertainties and other factors that could cause actual results to differ materially from expected results. There can be no assurance that LIM will be successful in maintaining any agreement with any First Nations groups who may assert aboriginal rights or may have a claim which affects LIM's properties or may be impacted by the Schefferville Projects. Shareholders and prospective investors should be aware that these statements are subject to known and unknown risks, uncertainties and other factors that could cause actual results to differ materially from those suggested by the forward-looking statements. Shareholders and prospective investors are cautioned not to place undue reliance on forward-looking information. By its nature, forward-looking information involves numerous assumptions, inherent risks and uncertainties, both general and specific, that contribute to the possibility that the predictions, forecasts, projections and various future events will not occur. LIM undertakes no obligation to update publicly or otherwise revise any forward-looking information whether as a result of new information, future events or other such factors which affect this information, except as required by law.