Birla Corporation Limited submitted the details of the Judgment of the Hon'ble High Court of Rajasthan, Jodhpur received by the Company on June 1, 2024. Nature and details of the action: The Judgment passed pertains to the penalty for excavating mineral limestone in excess, that is beyond the limit prescribed under the Environment Clearance issued by the competent authority. Details of the violation: The Hon'ble High Court has confirmed the penalty imposed by the Mining Engineer, Chittorgarh for violation of the provisions of inter-alia Rule 11(1) of the Mineral Conservation and Development Rules, 2017 for excavating excess limestone beyond the limit prescribed under the Environment Clearance issued by the competent authority.

Impact on financial, operation or other activities of the listed entity, quantifiable in monetary terms to the extent possible: INR 27,705,522. The Company believes that the above Judgment is appealable on various grounds and hence is in the process of preferring an appeal against the said Judgment.